Application Process
Duration
The total application process duration is comprised of but is not
limited to:
(1) The duration from the time of complete and accurate submission
of all the required documents to the first inspection; and
(2) The duration from the time of the final inspection to the
issuance of the licence/certification/registration approval or notice.
The duration for (1) and (2) is 5 working days and 2 working days
respectively.
The total application process duration does not cover that for
re-inspection and/or re-submission of the required documents - both of which are
dependent on the applicant's availability and meticulousness.
Fees
The fees to be paid is S$170 and should be made through a cheque
payable to 'National Environment Agency' No refund will be allowed once payment
has been made.
The National Environment Agency (NEA) collects personal information to carry out its various functions and duties under the National Environment Agency Act (Cap 195) including the implementation of environmental and public health policies in Singapore and any other related purposes. I hereby consent to NEA’s use of the information provided by me in the course of any application I have made to the NEA, to facilitate the processing of such application for such purposes. I hereby further consent to NEA sharing the information in such application with other Government agencies, or non-government entities authorised to carry out specific government services, unless prohibited by legislation.
|